NWFEG Asks Tacoma Power to Open Cowlitz Fisheries Work to Public Review

Nov 21, 2026 · @Larry Pryor

On November 20, 2026, the Northwest Fisheries Enhancement Group (NWFEG) sent Tacoma Power a formal request under License Article 405 of its FERC license for the Cowlitz River Hydroelectric Project (FERC No. 2016). We asked Tacoma to meet its long-standing obligation to keep the public informed about Cowlitz license-implementation work, and to solicit public comment on that work before decisions are made.

Tacoma Power staff, its contractors including the Washington Department of Fish and Wildlife (WDFW), technical subgroups and the Cowlitz Fisheries Technical Committee (FTC) produce studies, evaluations, draft plans and recommendations that shape the future of Cowlitz salmon and steelhead. In our experience, the public rarely sees this work until months after decisions are made, if at all. The most recent example is the FTC’s new Public Participation Protocol, dated October 22, 2026. It was confirmed at the November 3 FTC meeting and shared with the public on November 5. Our request to review it beforehand was declined.

We asked for a written response within 30 days, by December 21, 2026.

What Tacoma committed to, in its own words

Article 405 of Tacoma’s license required a Public Information Management Plan describing how Tacoma “will share and disseminate information and solicit public comment on implementing the provisions of the Settlement Agreement,” including “any recommendations and reports produced by the Fisheries Technical Committee.” Tacoma filed the plan on December 22, 2003, and FERC approved it as filed on June 10, 2004 (107 FERC ¶ 62,225). Article 405 states: “Upon Commission Approval, the plan becomes a requirement of the license, and the licensee shall implement the plan.”

In the plan and its accompanying filing, Tacoma committed that:

  • “All FTC recommendations will be made available for public review and comment in the form of draft implementation or design plans and study or monitoring reports.”
  • “The work products of these groups, as well as other plans and actions not specifically developed within the venue of a technical group but known to be of public interest, will be made available to the public for review and comment periodically throughout the term of the new license.”
  • Draft plans, reports and briefing notices would be distributed “as they become available for review and comment.”
  • Public briefings would “present new scientific findings and information, describe progress on the planning process and programs, and solicit input from the public on these actions.”
  • Tacoma would share this information “with a specific emphasis on the fisheries related actions.”

FERC approved the plan finding that “public comment will be solicited concerning the implementation of the provisions of the Settlement Agreement” and that it “provides ample measures for public involvement and information sharing.”

What we asked Tacoma to do

  1. Add NWFEG to the plan’s distribution list for draft plans, reports and briefing notices.
  2. Release Tacoma’s own license-implementation work, including studies, evaluations, monitoring reports and draft plans by staff, consultants, WDFW and subgroups, as it is developed.
  3. Release FTC recommendations and draft decision documents for public review and comment before FTC votes.
  4. Post FTC meeting materials ahead of meetings.
  5. Post every license-required plan and report in draft for public review, with a current status index.
  6. Post a schedule of review-and-comment opportunities on a Cowlitz web page.
  7. Actively solicit public comment, with comment periods of at least 30 days, notices through the website, distribution list, local media and project kiosks, and public briefings on major items.
  8. Identify what is pending now, including any extension or re-dating of the Fisheries and Hatchery Management Plan, the roughly $10 million Mayfield downstream collection project, fish health evaluations, monitoring reports and hatchery program reviews.
  9. Explain in writing any item Tacoma believes the plan does not cover.

This is not a public records request. These are commitments Tacoma made in its own license plan to share with the public as a matter of course.

Why it matters

Cowlitz salmon and steelhead returns have declined, seasons have closed, and anglers, guides and river communities have felt the effects for years. Tacoma Power spends millions of ratepayer dollars on Cowlitz fisheries each year. The plans, studies and recommendations behind that spending decide what happens next on the river.

For years, many in the angling community have shown up at meetings, written comments and raised concerns, only to see those comments summarized to a line or left unanswered, with decisions surfacing months later. Tacoma’s own plan says the public should see this work and be asked for input while it is still underway. Review and comment have meaning only if they happen before the decision.

NWFEG’s goal is a Cowlitz program the public can follow, understand and support. Timely access to the work, and a real chance to comment on it, is a straightforward place to start.

How you can take part

The plan says Tacoma’s outreach should follow public interest. Every person who asks shows that interest.

  1. Get on Tacoma’s distribution list. Email CowlitzFTC@tacoma.gov and cowlitz@cityoftacoma.org: “Please add me to the Cowlitz River Project distribution list under Section IV.2 of Tacoma Power’s Article 405 Public Information Management Plan. I’d like to receive draft implementation plans, reports, FTC recommendations and public briefing notices as they become available for review and comment, along with FTC meeting notices and materials.”
  2. Follow FERC filings. Create a free FERC Online account at ferc.gov and use eSubscription for docket P-2016. You’ll receive an email whenever anything is filed for the Cowlitz Project.
  3. Look up documents. Search FERC eLibrary for docket P-2016, and see Tacoma’s Cowlitz Fisheries Technical Committee and Cowlitz License Documents pages on mytpu.org.
  4. Request records. Tacoma Power and WDFW are subject to Washington’s Public Records Act.
  5. Comment. File an eComment at FERC in docket P-2016, email Tacoma at cowlitz@cityoftacoma.org, or speak during the FTC’s public comment period. Short, specific comments from your own experience on the river carry real weight.
  6. Join our request. Contact NWFEG at lpryor@nwfe.org to add your name or receive updates.

Documents

  • NWFEG, Article 405 Request — Timely Access to FTC and Tacoma Work Products, November 20, 2026 [link or PDF]
  • Tacoma Power, Public Information Management Plan, filed December 22, 2003, FERC eLibrary accession 20031224-0158 [link or PDF]
  • FERC, Order Approving Public Information Management Plan Under Article 405, 107 FERC ¶ 62,225, June 10, 2004, FERC eLibrary accession 20040610-3007 [link or PDF]
  • Tacoma’s posted copy of the plan: https://www.mytpu.org/wp-content/uploads/public-info-management-plan-art405.pdf
  • FERC eLibrary: https://elibrary.ferc.gov (search docket P-2016)

The Northwest Fisheries Enhancement Group advocates for healthy, abundant and harvestable Cowlitz River salmon and steelhead fisheries. Contact: Larry Pryor, Chairman, lpryor@nwfe.org, 509-292-6410.

Leave a Reply